|
Public
Menu - 2006 Minutes
- 2007 Minutes -
2008 Minutes
Commission Minutes
GREENWOOD METROPOLITAN DISTRICT
MINUTES OF THE
January 14, 2009
Regular meeting
The regular meeting of the
Greenwood Metropolitan District Commission was held
Wednesday, January 14, 2008 at 3:00 p.m., in the Conference
Room of Greenwood Metropolitan District’s Technical Service
Facility, 110 Metro Drive, Greenwood, SC 29646.
In attendance:
Commissioner Bob Haynie,
Chairman
Richard Coleman Lesley Lane
Commissioner Byron Smith,
Vice Chairman George Martin
Marsha Meyer
Commissioner Gene Hancock,
Secretary
Marion Boone Bill Moore
Commissioner Michael G.
Monaghan
Daniel Clark Jamie Peeler
Commissioner Henry Watts
Wayne Daniel Steve Pohlman
Commissioner Tim
Burke
Ken Davis Brian Waldrep
Gayle Grogan Danny Ware
Roy Hemphill Mark Warner
Paige Holley Tony Williamson
I.
Chairman Haynie called the meeting to order and gave
the statement of compliance with the notification
provision of the Freedom of
Information Act.
II.
George Martin gave the invocation.
III.
Due to the expansion at Technical Service Facility (TSF)
the Board Meeting was held in the conference
room and the recording
system was unavailable. The minutes are based on notes
taken by Mrs. Holley.
IV.
Wilson Creek Plant Update
Mr. Danny Ware from Davis
and Floyd, Inc. (D&F) said he will give the monthly report
at the next meeting. The monthly progress meeting for
January will be Thursday, January 22nd.
Blanchard arrived today to work on the generators. The new
generators will be installed next week. The completion date
for the generators and electrical work is February 2nd.
Overall the contractor is reporting the construction to be
two months ahead of schedule.
V.
TSF Expansion
Mr. Bill Moore from D&F
provided the Commission with an update on the expansion.
The sheetrock installation is complete with emphasis now on
repairing, priming and preparation for final coat of paint.
The majority of the ceiling grid is in place. Lighting
fixtures are approximately 90% completed. The countertops
in the kitchen and collection department rooms are
installed. The weather has been a factor in completing the
roof parapet and EIFS system, but they are over 95%
complete. Pay request numbers 7 & 8 are being held until a
revised construction schedule from the contractor has been
received. During the next two weeks the contractor hopes to
finish painting the walls, have the floor covering complete
except for carpeted areas. The contractor hopes to start
installing the tack wall and folding partition in the
Commission Room and Training Room. There was some
discussion on change order ‘e” as listed on the report from
Mr. Moore. Some of the Commissioners are under the
impression the change order has been approved. Per the
Commission meeting minutes on December 3rd only
the design modification was approved. “Commissioner
Smith made a motion to approve the design modification to
the Server Room costing $4,800; Commissioner Watts seconded,
and the motion was unanimously approved.”
VI.
Commissioner Watts made a motion to approve the
December 3, 2008 minutes as amended;
Commission Smith seconded,
and the motion was unanimously approved.
VII.
Service Reports
a.
Collection System
It was noted that one of the
four grinder pumps that were disconnected was reconnected on
January 9th. DHEC and the County are aware of
the disconnections. The three homes that are still
disconnected have not contacted Metro. The grinder pump
expenses over the last two years is $10,218.42 more than
revenue collected.
b.
Engineering
The County identified the 60
failing septic tanks on Lakeshores. The County has applied
for a grant for that area. The collection line repair on
Fourth Street will be done by Metro personnel.
c.
I/I Abatement
The Seaboard Project is in
the design phase. Commissioner Monaghan inquired about the
Turner Branch Project. Mr. Boone said the contractor is
making some headway, but the weather has been a factor. The
City Pond project is about 25% complete. The contractor for
City Pond was granted permission to work on Saturdays. The
overtime is needed so the contractor can meet the completion
date.
VIII.
Action Items
a.
Ratify Change of Chemical Supplier
Mr. Peeler explained to the
Commission the need and reason why Metro wants to change the
supplier of Magnesium Slurry. The recommendedvendor for
this product is Brenntag and Metro has used their product
before with success. Chairman Haynie inquired if Metro
asked for a sample of the products when soliciting bids.
Mr. Peeler said Metro did receive samples and no problems
were discovered while using the samples. Metro has tried to
work with the supplier. It is the recommendation of staff
to remove the current supplier from the bid listing.
Commissioner Watts made a
motion to change the chemical supplier for Magnesium Slurry
to Brenntag; Commissioner Hancock seconded, and the motion
was unanimously approved.
b.
Consideration of Change Orders for Wilson Creek Plant
Upgrade
i.
Change Order #11
Addition of 6” Containment
Curb for screen conveyor at IPS. Cost is $1,332.58
ii.
Change Order #12
Add concrete fill in UV
chamber for improved cleaning. Cost is $1,946.91.
iii.
Change Order #13
Stairway slab extension for
BNR #1 and BNR #2. Cost is $7,674.74.
Commissioner Monaghan made a
motion to approve change orders #11, #12 and #13 for a total
cost of $10,954.23; Commissioner Smith seconded, and the
motion was unanimously approved.
c.
Consideration of Martin Luther King Jr. Holiday
Commissioner Hancock (on his
birthday) made a motion to add Martin Luther King, Jr Day as
a granted holiday; Commissioner Monaghan seconded, and the
motion was unanimously approved.
IX.
Old Business
a.
GO Bond
Manager Coleman said Metro
does not have the assessed value in the millage account.
Chairman Haynie said he received the information this
afternoon. Metro did approve a resolution to reimburse
themselves on August 20, 2008. The process to issue a bond
takes an average of 90 days. Chairman Haynie had received
the assessed value form the County this afternoon without
the fee-in-lieu of taxes included. The assessed value is
$186,967,073.
X.
Miscellaneous Administrative Matters
a.
Invitation for Chamber’s Annual Meeting
The Commissioners are to
inform Mrs. Grogan if they plan to attend the meeting.
Spouses are welcome to attend.
XI.
Commissioner Watts made a motion to go into Executive
Session to discuss a legal and personnel matter;
Commissioner Hancock
seconded, and the motion was unanimously approved.
XII.
The meeting returned to open session. No action was
taken during executive session.
XIII.
With no further business, the meeting was adjourned.
|