Main Menu

Home

GMD Commissioners

About Us

Customer Service

Education & Tours

Public Information

County Links

County GIS System

 

GMD Public Information

Public Menu2006 Minutes - 2007 Minutes - 2008 Minutes

Commission Minutes

GREENWOOD METROPOLITAN DISTRICT

MINUTES OF THE January 14, 2009

Regular meeting

 

The regular meeting of the Greenwood Metropolitan District Commission was held Wednesday, January 14, 2008 at 3:00 p.m., in the Conference Room of Greenwood Metropolitan District’s Technical Service Facility, 110 Metro Drive, Greenwood, SC 29646.

 

In attendance:

Commissioner Bob Haynie, Chairman                     Richard Coleman         Lesley Lane

Commissioner Byron Smith, Vice Chairman            George Martin             Marsha Meyer

Commissioner Gene Hancock, Secretary                 Marion Boone              Bill Moore

Commissioner Michael G. Monaghan                      Daniel Clark                Jamie Peeler

Commissioner Henry Watts                                     Wayne Daniel              Steve Pohlman

Commissioner Tim Burke                                        Ken Davis                    Brian Waldrep

                                                                                Gayle Grogan               Danny Ware

        Roy Hemphill               Mark Warner

        Paige Holley                 Tony Williamson

 

 

I.          Chairman Haynie called the meeting to order and gave the statement of compliance with the notification

         provision of the Freedom of Information Act.

 

II.          George Martin gave the invocation. 

 

III.          Due to the expansion at Technical Service Facility (TSF) the Board Meeting was held in the conference

           room and the recording system was unavailable.  The minutes are based on notes taken by Mrs. Holley.

 

IV.          Wilson Creek Plant Update

Mr. Danny Ware from Davis and Floyd, Inc. (D&F) said he will give the monthly report at the next meeting.  The monthly progress meeting for January will be Thursday, January 22nd.  Blanchard arrived today to work on the generators.  The new generators will be installed next week.  The completion date for the generators and electrical work is February 2nd.  Overall the contractor is reporting the construction to be two months ahead of schedule. 

 

V.          TSF Expansion

Mr. Bill Moore from D&F provided the Commission with an update on the expansion.  The sheetrock installation is complete with emphasis now on repairing, priming and preparation for final coat of paint.  The majority of the ceiling grid is in place.  Lighting fixtures are approximately 90% completed.  The countertops in the kitchen and collection department rooms are installed.  The weather has been a factor in completing the roof parapet and EIFS system, but they are over 95% complete.  Pay request numbers 7 & 8 are being held until a revised construction schedule from the contractor has been received.  During the next two weeks the contractor hopes to finish painting the walls, have the floor covering complete except for carpeted areas.  The contractor hopes to start installing the tack wall and folding partition in the Commission Room and Training Room.  There was some discussion on change order ‘e” as listed on the report from Mr. Moore.  Some of the Commissioners are under the impression the change order has been approved.  Per the Commission meeting minutes on December 3rd only the design modification was approved.  “Commissioner Smith made a motion to approve the design modification to the Server Room costing $4,800; Commissioner Watts seconded, and the motion was unanimously approved.” 

 

VI.          Commissioner Watts made a motion to approve the December 3, 2008 minutes as amended;

           Commission Smith seconded, and the motion was unanimously approved. 

 

VII.          Service Reports

a.      Collection System

It was noted that one of the four grinder pumps that were disconnected was reconnected on January 9th.  DHEC and the County are aware of the disconnections.  The three homes that are still disconnected have not contacted Metro.  The grinder pump expenses over the last two years is $10,218.42 more than revenue collected. 

 

b.     Engineering

The County identified the 60 failing septic tanks on Lakeshores.  The County has applied for a grant for that area.  The collection line repair on Fourth Street will be done by Metro personnel. 

 

c.      I/I Abatement

The Seaboard Project is in the design phase.  Commissioner Monaghan inquired about the Turner Branch Project.  Mr. Boone said the contractor is making some headway, but the weather has been a factor.  The City Pond project is about 25% complete.  The contractor for City Pond was granted permission to work on Saturdays.  The overtime is needed so the contractor can meet the completion date. 

 

VIII.          Action Items

a.      Ratify Change of Chemical Supplier

Mr. Peeler explained to the Commission the need and reason why Metro wants to change the supplier of Magnesium Slurry.  The recommendedvendor for this product is Brenntag and Metro has used their product before with success.  Chairman Haynie inquired if Metro asked for a sample of the products when soliciting bids.  Mr. Peeler said Metro did receive samples and no problems were discovered while using the samples.  Metro has tried to work with the supplier.  It is the recommendation of staff to remove the current supplier from the bid listing. 

 

Commissioner Watts made a motion to change the chemical supplier for Magnesium Slurry to Brenntag; Commissioner Hancock seconded, and the motion was unanimously approved.

 

b.     Consideration of Change Orders for Wilson Creek Plant Upgrade

                                                    i.     Change Order #11

Addition of 6” Containment Curb for screen conveyor at IPS.  Cost is $1,332.58

 

                                                  ii.     Change Order #12

Add concrete fill in UV chamber for improved cleaning.  Cost is $1,946.91.

 

                                                iii.     Change Order #13

Stairway slab extension for BNR #1 and BNR #2.  Cost is $7,674.74.

 

Commissioner Monaghan made a motion to approve change orders #11, #12 and #13 for a total cost of $10,954.23; Commissioner Smith seconded, and the motion was unanimously approved. 

 

c.      Consideration of Martin Luther King Jr. Holiday

 

Commissioner Hancock (on his birthday) made a motion to add Martin Luther King, Jr Day as a granted holiday; Commissioner Monaghan seconded, and the motion was unanimously approved. 

 

IX.          Old Business

a.      GO Bond

Manager Coleman said Metro does not have the assessed value in the millage account.  Chairman Haynie said he received the information this afternoon.  Metro did approve a resolution to reimburse themselves on August 20, 2008.  The process to issue a bond takes an average of 90 days.  Chairman Haynie had received the assessed value form the County this afternoon without the fee-in-lieu of taxes included.  The assessed value is $186,967,073.

 

X.          Miscellaneous Administrative Matters

a.      Invitation for Chamber’s Annual Meeting

The Commissioners are to inform Mrs. Grogan if they plan to attend the meeting.  Spouses are welcome to attend.

 

XI.          Commissioner Watts made a motion to go into Executive Session to discuss a legal and personnel matter;

           Commissioner Hancock seconded, and the motion was unanimously approved. 

 

XII.          The meeting returned to open session.  No action was taken during executive session.

 

XIII.          With no further business, the meeting was adjourned.

 

 

 

 

Use Advanced Search