|
Public
Menu - 2006 Minutes
- 2007 Minutes
Commission Minutes
GREENWOOD
METROPOLITAN DISTRICT
MINUTES OF THE October 24, 2007
Regular Meeting
The regular meeting of the
Greenwood Metropolitan District Commission was held
Wednesday, October 24, 2007, at 3:00 p.m., in the Board Room
of CPW/Greenwood Metropolitan District Administrative
Building, 121 West Court Avenue.
In attendance:
Commissioner Bob Haynie,
Chairman
Richard Coleman Marsha Meyer
Commissioner Byron Smith,
Vice Chairman George Martin Michael Nix
Commissioner Gene Hancock,
Secretary Wayne Daniel Joe Swofford
Commissioner Michael G.
Monaghan
Gayle Grogan Brian Waldrep
Commissioner Henry
Watts Roy
Hemphill Danny Ware
Commissioner Tim
Burke Paige Holley
-
Chairman Haynie called
the meeting to order and Mr. Martin gave the invocation.
-
Chairman Haynie gave the
statement of compliance with the notification provision
of the Freedom of Information Act.
-
Bids on Easement Machine
Bidder Amount
Adam’s
Equipment $26,381.92
Jet-Vac
$31,235.44
Rodders and
Jets $27,991.00
3T Equipment Company, Inc
$30,610.00
Staff will review the bids to
assure compliance with the specifications. If the bid is in
compliance, the bid will be awarded to the apparent low
bidder, Adam’s Equipment at the next Board Meeting.
-
Wilson Creek Update
Mr. Ware reported the
contractor is finishing up phase 1A. Everything is almost
complete with the exception of dressing up. Davis and Floyd
will have a walk through inspection tomorrow morning
Thursday, October 25th to generate punch list
items for the contractor to correct and fix. All of the
grading work has been done; the trailers have been removed.
Chairman Haynie asked if the punch list is extensive. Mr.
Ware responded the preliminary punch list is about 2 pages
of small items. Chairman Haynie asked how much did the
contractor actually use of the penalty phase time. Mr. Ware
responded 144 days; the liquidated damages are $72,000.
Commissioner Monaghan asked if the penalty days stop now
with the punch list items. Mr. Ware said substantial
completion was reached on August 31st; the
contractor has 60 days from that date to complete; which
will be November 6th. As long as the punch list
items are addressed before November 6th, the
contractor will meet the final completion date. If the
contractor does not meet the date, there are additional
liquidated damages to be assessed beyond the $72,000.
Manager Coleman said at the substantial completion date the
liquidated damages were stopped. Commissioner Monaghan
inquired how much money is Metro withholding. Mr. Ware
responded they are still withholding about $700,000 and
about $300,000 of that is retainage. Commissioner Monaghan
commented the plant is fully commissioned. Mr. Ware said
Metro was granted an operational permit on August 31st
and it has been operating since. After the clarifiers were
operational, the contractor had to do additional work. Mr.
Ware stated Davis and Floyd advertised on October 14th
and 21st for phase 1B. So far Davis and Floyd
has sent out 25 sets of documents, but only about 6 of those
are for prime bidders. The pre-bid meeting is Thursday,
November 8th. Commissioner Monaghan wanted to
know where the notice was advertised. Mr. Ware responded it
was advertised in the Greenville News, The State and the
Index Journal. It was also advertised in the AGC office,
the Dodge Office and the reconstruction data office.
Commissioner Watts asked if the contractor for phase 1A
requested documents on phase 1B. Mr. Ware responded yes,
the contractor has secured a set of documents. Commissioner
Monaghan wanted to know the status of the Value
Engineering. Mr. Ware said they have addressed the comments
and filled out a response that has been submitted.
Commissioner Monaghan said he is scared about change
orders. Mr. Ware said hopefully the review process along
with the QAQC review should lower the number of change
orders. Commissioner Watts inquired on what is the normal
percentage of change orders. Mr. Ware responded generally
on a bare site the number is 3%; on an existing site the
number is 5%.
-
Commissioner Burke asked
for an update on the expansion of the Technical Service
Facility (TSF). Mr. Ware said he is not involved in
that and therefore does not know the status of the
project. Mr. Martin said Mr. Moore has asked for some
information which Mr. Waldrep has provided. Davis and
Floyd is working on it.
-
Commissioner Monaghan
made a motion that the minutes from the September 26,
2007 Regular Meeting be approved as mailed and
Commissioner Hancock seconded. The motion was
unanimously approved.
VII.
Financial Report
-
Mr. Michael Nix of
Greenwood Capital gave a report on the District’s
portfolio. The 1081 account represents the general
reserve account. Mr. Nix pointed out that the first
page shows which bonds have matured, sold or called
during the fiscal year. The next two pages are the
statement for the account. Commissioner Monaghan
asked if Metro earns interest on the money market.
Mr. Nix responded yes and the interest is around
4.5%. Mr. Nix said at no point is the money/cash
sitting idle. If a bond pays interest it is
automatically swept into a money market; it would
stay in the money market until it goes to a new
issue for purchase. Commissioner Monaghan asked if
the gain or loss is shown. Mr. Nix said it is
reflected on the income of the account, but it is
not reflected on these statements. Page four is the
performance report for the account as of September
30, 2007. The $600,000 is from proceeds from the
sell of the Administrative Building. A big part of
the withdrawals are for the Cambridge Avenue
Project. The realized gains are bonds that have
been sold or matured during the period. The
unrealized gains are bonds that are still held but
there is a change in value. The difference is the
interest that has been paid off of the bonds. Mr.
Nix directed the Commission to the next account
which is the 1082 (Capacity) account. On page five
it shows the bonds have matured or came due during
the period. Mr. Nix said page six & seven reflect
the assets in the account. Page eight shows the
beginning value as of June 30, 2007, contributions
($45,000 roughly was for Newport Subdivision Phase
2), realized gains and losses, interest generated on
the account and then the change in value. Mr. Nix
stated page nine is the Bond Proceed Account. He
reminded the Board this account is designed to have
bonds maturing at specific periods to meet draw
schedules. Commissioner Monaghan said these are
revenue bond proceeds that are still unspent.
Commissioner Monaghan said Metro does not want to
accrue any arbitrage on the bonds. He asked does
the money spent have to be used for what the bond
was obtained for. Commissioner Monaghan said the
reason he is asking is would Metro not want to spend
the bond revenue before they start spending the
reserves that are not designated. Manager Coleman
responded Metro cannot say they are going to issue a
bond for a certain reason and spend the money on
something else. Commissioner Monaghan said Metro is
still going to spend the money. Manager Coleman
said Metro cannot issue the bonds for one thing and
spend the money on something else. Commissioner
Monaghan wanted to know who says that Metro cannot
do that. Manager Coleman responded the Board says
it when they issue the bond. Metro has to say what
they are issuing the bonds for. Commissioner
Monaghan said as long as Metro is going to do the
project and the project gets done what difference
does it make on where the money comes from. He
thinks that Metro would want to get rid of the
revenue bond money first so they don’t get in any
arbitrage issues. Mr. Hemphill said he is not aware
of the amount left in the bond. Commissioner
Monaghan said quite a bit of money. Manager Coleman
said Metro has not reached the end of the bond
period. Commissioner Monaghan said he knows Metro
has not. He wanted to know why Metro takes the
money out of the Reserve Account before they take
money out of the Revenue Bond. Manager Coleman said
when Metro issues a bond they are required to say
what the bond is for. Metro can then only spend the
bond money for what they say it is for within the
designated time period. Commissioner Monaghan said
he is not sure. He feels that as long as Metro does
the project; Metro has fulfilled the requirements of
the revenue bond. Commissioner Burke inquired if
there is a legal obligation. Chairman Haynie said
he thought that was the way the bond was written.
Mr. Hemphill said that is his thought too. Metro is
to follow the track of how the bonds are issued.
Mr. Hemphill will check with Metro’s bond counsel on
this item. Commissioner Hancock said Metro can
repay themselves back from the bonds for any money
spent on the project prior to the bond being issued
for the designated projects. Mr. Nix said on page
ten of the report the cash amount is roughly
$900,000 as of September 30, 2007. Page eleven of
the report is the performance breakdown for the Bond
Proceed Account. Metro is generating a fair amount
of income on the bonds. Fiscal year-to-date Metro
has generated $113,000 in income on the Bond Proceed
Accounts. Commissioner Monaghan wanted to know who
tracks the end dates for the bonds. Manager Coleman
replied the IRS and they can track the bonds in
arrears. Commissioner Monaghan wanted to know if
someone at Metro tracts the bonds. Manager Coleman
said Metro knows when the account is opened and
closed. Chairman Haynie asked if Metro can amend
the bond. Commissioner Burke said for an overage
within the project. Mr. Hemphill said the bond
usually states for an “amount not exceeding”.
Chairman Haynie said he is talking about any excess
funds left in the bond. Commissioner Monaghan
inquired if Metro had ever paid the arbitrage
penalty. Manager Coleman responded no. Mr. Nix
said there has been a decline in the interest
rates. From what Mr. Nix is able to see based on
different reports, companies are doing very well
overseas but the ones domestically are saying the
United States is in a recession.
-
Chairman Haynie asked
for questions from the Board on the Financial
Report. He noted on page 17 under sewer service
even with the 8% increase the income is still
static. Manager Coleman said Metro started out the
fiscal year with the first month behind and it is
maintaining the shortfall. Commissioner Monaghan
noted Metro is $74,000 favorable to budget and Metro
has not received any tax revenue. Manager Coleman
said the water sales (usage) are down; primarily in
industrial sales. Commissioner Monaghan inquired
who was the biggest industrial user. Manager
Coleman replied the biggest one is Fuji and then
Solutia. He reminded the Board that Fuji has
decreased their usage due to the closing of an old
line. Metro has changed Fuji’s permit to reflect
the line closing. Commissioner Monaghan commented
that Metro is doing a good job of containing
expenses. Commissioner Monaghan noted that all
departments are doing well containing their
expenses; they are all under budget. Chairman
Haynie asked Manager Coleman if there are any items
that he would like to address. Commissioner
Monaghan referenced page 24 of the packet he said on
the 2006 GO Bond; he wanted to know what the
$327,417 represents. Mrs. Grogan replied that is
the remaining proceeds Metro has left to spend in
the account. Commissioner Monaghan said he did not
see the 2006 GO Bond listed on page 19 of the
packet. Mrs. Grogan responded it is in the list at
the top of the page. Commissioner Monaghan asked if
Metro owes more money. Mrs. Grogan said in June
Metro paid in full for the GO Bond. Commissioner
Monaghan said that is why it is not listed on the
bottom part on page 19. Mrs. Grogan responded yes,
that is correct. Commissioner Monaghan inquired
where the proceeds from the 2006 GO Bond are going
to be used. Mrs. Grogan replied it will be used on
the Cokesbury and Turner Branch Projects.
Commissioner Monaghan asked if that is the amount to
be paid. Mrs. Grogan responded those are the dollar
amounts that have been paid for this fiscal year.
Commissioner Monaghan asked if Metro anticipates
having problems from the County on getting the money
out. Manager Coleman replied the money is already
out. Commissioner Monaghan said that is not what
the spreadsheet says. Mrs. Grogan said this is
proceeds that Metro can pay for those projects.
Commissioner Monaghan said the money is still in a
County account. Mrs. Grogan said yes. Chairman
Haynie stated Metro met all of the County’s
requirements for Metro to use that money. Mrs.
Grogan stated the Millage Account is the one where
the County would not allow Metro to use the money.
Commissioner Monaghan asked if these were two
different accounts. Mrs. Grogan replied yes.
Commissioner Monaghan said he liked having the
monthly explanation of overage/underage for each
department ahead of time.
VIII.
Action Items
-
Bond Resolution
Chairman Haynie stated Metro
has a resolution confirming the intention of Greenwood
Metropolitan District to be reimbursed for certain
expenditures related to capital projects to be financed by
the issuance of bonds. He said this resolution will allow
Metro to reimburse themselves for any money that was spent
in advance for the capital projects that are related to the
bonds. Commissioner Monaghan wanted to know how much money
is Metro going to ask for. Chairman Haynie said the bond is
not to exceed $40 million. Manager Coleman said right now
it is around $30 million. He said the reason the amount was
set high is because Metro has not actually received the
bids. Commissioner Monaghan said in the minutes from the
September 12th meeting it says “Metro is
borrowing $20 million now and will borrow about $15 million
in two to three years”. Manager Coleman said the numbers
changed after the bond meeting. He said at the September 26th
meeting he explained that “Metro is looking at the
possibility of issuing a $30 million bond now and wrapping
that around the current debt.” Manager Coleman said bids
will not be received until December 5th or 8th.
If needed this will give Metro time to adjust what is
actually borrowed. Manager Coleman said Metro was looking
at not having to issue two bonds for the same project.
Commissioner Monaghan wanted to know why that would make a
difference. Manager Coleman said there would be one less
issuance cost. Commissioner Monaghan asked if Metro has
looked at the interest rate since they are going down.
Commissioner Burke said Metro would be in better shape in
January. Manager Coleman said right now the interest rate
is relatively low and there is not much difference between
the front end and back end of the bond. Commissioner
Monaghan wanted to know if Metro borrows the larger amount
can it be paid off within the arbitrage limit. Manager
Coleman replied yes, that is what Metro is anticipating.
Manager Coleman noted that Metro was trying to make sure the
amount would fit into the rate structure and to ensure that
Metro will have the amount of coverage that is needed.
Commissioner Monaghan asked if Metro had a requirement on
the bid that stated there would be a penalty for being late
and he wanted to know if that was smart. Manager Coleman
said Metro now has a 2 ½ year project instead of a nine
month project. Metro knew they needed to have phase 1A done
as quickly as possible. Manager Coleman said Metro is not
under a deadline for the project. Commissioner Monaghan
asked if Metro was going to have a penalty. Manager Coleman
replied Metro will have a penalty for going over.
Commissioner Monaghan wanted to know when the 6’ pipe is
going to be installed. Mr. Martin replied Metro will talk
about that in a few minutes.
Commissioner Hancock made the
motion to approve the bond resolution; Commissioner Smith
seconded, and the motion was unanimously approved.
-
Miscellaneous
Administration Matters
-
The meeting to
discuss the Long Range Planning was set for
Wednesday, November 14, 2007, at 10:00 am at TSF. A
lunch will be provided.
-
Commissioner Monaghan
asked for an update on the trailer situation. Mr.
Martin replied no work has been done on the trailer
situation since the last meeting. Commissioner
Monaghan wanted to know why. Commissioner Monaghan
asked for Metro to find out if a legal document is
made, will the Highway Department accept it. Mr.
Hemphill is to draft a legal document regarding the
trailer situation for the Board to sign. The
document will then be taken to the Highway
Department to see if Metro can obtain tags for the
trailers. Commissioner Hancock inquired about the
forms for the Certificate of Origin. Mrs. Meyer
replied that is what Metro does not have.
Commissioner Hancock asked who would have the
Certificate of Origin. Commissioner Burke said the
manufacturer provided one when the trailers were
purchased.
-
Commissioner Monaghan
asked if the distribution cost has been calculated.
Mr. Martin responded that has been done.
Commissioner Monaghan asked for Mr. Martin to send
an email to the Board with the cost.
-
Commissioner Monaghan
wanted to know what pecan trees are to be relocated
and why. Commissioner Hancock said they are on the
right hand side going down to the plant.
Commissioner Monaghan asked why Metro wanted to
relocate them. Manager Coleman responded that Mr.
Pohlman asked to see if we could relocate them. He
said if Metro does that it would be outside of the
1B contract.
-
Commissioner Monaghan
stated that usually procedures are ratified by the
Board. He noted that Metro has a Biosolids
Distribution Procedure. Commissioner Monaghan asked
if that was ratified by the Board. Mr. Martin
responded no. Commissioner Monaghan asked if the
procedures should be ratified. Mr. Martin replied
yes. Commissioner Monaghan wanted to know when the
Board will ratify the procedures. Mr. Martin
replied the procedures will be brought to the Board
once corrections and changes have been made.
-
Commissioner Monaghan
noted that he gave Mr. Martin an analysis from
Carlos Cometto (CPW in-house engineer). He said the
one thing that CPW is concerned about is having
access on the other side of the pond. Mr. Martin
said Commissioner Monaghan just handed the
information to him and he has not had a chance to
review it. Mr. Martin said this line is put in the
route Metro would take if it was a trunkline.
Commissioner Monaghan said it should be and that is
why he gave it to Mr. Martin. He said if that other
way can’t be done, it can’t be done. Mr. Martin
said they will look at it.
-
Commissioner Monaghan
inquired on the status of the physical inventory
policy and procedure. Manager Coleman said Metro
would have it done by the end of the fiscal year.
Commissioner Monaghan wanted to know if anyone was
going to help Metro. Mr. Martin said yes.
Commissioner Monaghan suggested Elliott Davis as the
auditing firm to help with the procedures. He said
it is very important for Metro to have a good
procedure and then Metro is supposed to work on the
differences between Peachtree and CASSWORKS.
Commissioner Monaghan said the programmers should be
working on that issue. Mr. Martin said he and Mr.
Waldrep have talked about that issue; the conclusion
that they came up with is Peachtree will do exactly
what it is supposed to do as far as accounting.
Mrs. Grogan said whatever is keyed into Peachtree is
paid out. Mr. Martin said with CASSWORKS Metro can
do the inventory and those two number can both
balance exactly. Commissioner Monaghan said so
Metro can check them. Mr. Martin replied yes, but
Metro cannot make Peachtree and CASSWORKS talk to
each other. Commissioner Monaghan asked if it is
necessary to make them talk. Mr. Martin responded
he thinks it works fine the way it currently is.
Mrs. Meyer said that she thinks Metro would spend so
much money trying to make them talk that Metro could
invest into a new program. Mr. Martin said from the
inventory control side Metro knows what they have.
He said from the expenditure side Mrs. Grogan knows
exactly what has been paid. Mrs. Grogan said that
she checks to make sure everything has been cleared
out that was keyed in. She said there are no
purchase orders in the system because no purchase
orders have been issued through Peachtree. Mr.
Martin stated all purchase orders are issued through
CASSWORKS. Commissioner Monaghan wanted to know if
a purchase order is seen before the invoice is
paid. Mrs. Grogan replied Mrs. Gray (Account
Payable Clerk) pulls them from CASSWORKS to match it
with the invoice. Commissioner Monaghan said Mrs.
Gray gives the receiving report, the invoice and the
purchase order to Mrs. Grogan. Mrs. Grogan said
Mrs. Gray gives her the invoice with the receiving
report and she (Mrs. Gray) has already checked the
information before the check has been issued.
Commissioner Monaghan said Metro needs to see the
purchase order and receiving report. Mrs. Meyer
said Mrs. Gray does see the purchase order in the
computer and once she sees that she prints out the
receiving report. Commissioner Monaghan asked if
the purchase order has a signature on it. Mr.
Martin replied his signature is on all purchase
orders. Commissioner Hancock said every check has
the supporting paperwork attached. Commissioner
Monaghan said he wanted to make sure before the
invoice is paid the purchase order, receiving report
and invoice are checked. Mrs. Grogan said Mrs. Gray
checks all of that information before she gives it
to her to print checks. Commissioner Monaghan said
he really has a problem with the assets. He said at
his company when an asset was scraped they had to
have documentation that the asset was scraped and
the asset tag; all of that information went to the
accountant and the accountant removed it from the
asset list. Commissioner Monaghan said if Metro
keeps valuing assets and assets than Metro is
overstating their worth. He hopes that Metro
enlists Elliott Davis to help. Mrs. Grogan said she
has talked with Laurie at Elliott Davis, but it will
take a while to get all the information together.
She said it will not be done in a month’s time.
Mrs. Grogan said staff is limited as to when they
can leave the office to go out and check the
assets. Commissioner Monaghan said usually for a
physical inventory at the end of the fiscal year
everybody shuts down. Commissioner Monaghan said
the Board can even help. Chairman Haynie suggested
doing the physical count on a Saturday.
Commissioner Monaghan said usually everybody shut
downs and does the physical inventory and the
accountant makes sure it is done right. The
accountant is going around and testing. The
physical count would then be reconciled with the
books and anything that is not there is written
off. Commissioner Hancock said the biggest part of
the inventory is repair parts. Commissioner
Monaghan said Metro has cars, trucks, etc.
Commissioners Hancock said other than equipment and
big trucks; the rest of it is repairs parts. Mrs.
Grogan said that Mr. Smith (receiving agent) gives
her a supply room inventory report every month.
-
Commissioner Monaghan
inquired on the status of Eagles Harbor. He said
The Index Journal said there will be another
meeting. Commissioner Burke said there is to be a
meeting with the Homeowner Association of Eagles
Harbor in order to establish if they will annex into
Metro’s district and what the participation is going
to be within their subdivision. Commissioner
Monaghan said there are areas within the Metro
District that have been paying taxes for years. He
asked how Metro could run a line to a new
subdivision without serving those areas that wanted
sewer for years unless they pay for it.
Commissioner Burke asked how could Metro justify
spending $4 million on 60 independently owned lots.
Commissioner Hancock said the biggest thing is the
State messed up. Commissioner Monaghan said if the
State funds it Metro would be happy to provide
service. He said he would like to have the sewer
extend to Virgin Heights. Manager Coleman said all
Metro has talked about is getting the sewer up to
Virgin Heights area with a pump station that would
receive Eagles Harbor. Eagles Harbor would be
responsible for getting the sewer to that point.
Commissioner Monaghan said he thought if Metro
installed a trunkline Eagles Harbor would have to
tap in whether they wanted to or not. Commissioner
Burke said DHEC will not issue additional septic
permits after the trunkline is available, but there
are roughly 20 homeowners that have already spent
$18,000 to $20,000 on an engineered septic system.
Commissioner Monaghan wanted to know the difference
between an engineered septic system and a
non-engineered septic system. Commissioner Burke
said an engineered septic system is a mechanically
lifted system. Manager Coleman said if Eagles
Harbor can come to the Metro trunkline, Metro will
consider getting the sewer up to Virgin Heights. He
said some homeowners have met with Metro to find out
what steps they will need to take in order to
finance the sewer collection system.
-
Commissioner Monaghan
wanted to know if Metro was finished with the Shrine
Club Road Project. Mr. Martin responded no, but the
contractor is now hooking up the pumps.
-
Mr. Martin said he
was asked to present to the Board a request from
Calhoun Mays regarding some property across from
Mathews Elementary School and Mathews United
Methodist Church. Metro’s sewer line presently goes
across those properties. Mr. Martin asked if the
Board would install a new sewer line and abandon the
old line for those pieces of property. Chairman
Haynie asked if this would be at Metro’s expense.
Mr. Martin replied yes. Chairman Haynie said so Mr.
Mays would be able to sell those lots. Mr. Martin
replied yes. Commissioner Burke asked if Metro has
a right-of-way. Mr. Martin said Metro does have a
right-of-way. He said Mr. Mays has not purchased
the property, but he is looking at it. Mr. Martin
said he was asked by Mr. Mays to bring the question
to the Board. Commissioner Monaghan said it is good
that people are thinking about developing around
that area, but he is not sure that Metro should pay
for it. Chairman Haynie said typically if someone
was doing a subdivision the developer installs the
lines and Metro accepts them. Commissioner Monaghan
said Mr. Mays would get from both the City and CPW
incentives for doing that. Mr. Martin noted that he
shared that information with Mr. Mays. Commissioner
Monaghan stated Mr. Mays would get a tax write off
from The City and he would get a utility
reimbursement for each house that is developed.
Chairman Haynie said he does not see how Metro can
move the line. Commissioner Monaghan asked how
would that work. Mr. Martin said Mr. Mays would
have to offset it and install a collection line
between them to serve the area. Commissioner
Hancock said Mr. Mays needs to go to The City and
CPW first.
-
Partnership /
Economic Alliance
Commissioner Monaghan said
that he and Chairman Haynie are scheduled to have a
financial meeting on October 31st. Commissioner
Hancock commented that there are some businesses that are
going into the empty box buildings.
-
Commissioner Smith made a
motion to go into Executive Session to discuss a
contractual matter; Commissioner Watts seconded, and the
motion was unanimously approved.
-
The meeting returned to
open session. No action was taken during executive
session.
XII.
Commissioner Monaghan made a motion to accept The
Davis’ offer of $185,600 to also include that the buyer
would pay any roll back applicable and to allow the hunting
lease to extend through the end of the season (January 1,
2008); Commissioner Hancock seconded, and the motion was
unanimously approved.
XIII.
With no further business, the meeting was adjourned.
|